Nev. Rev. Stat. § 338.1691
Qualifications for construction manager at risk
Text of § 338.1691
To qualify to enter into contracts with a public body for preconstruction services and to construct a public work, a construction manager at risk must:
1. Not have been found liable for breach of contract with respect to a previous project, other than a breach for legitimate cause, during the 5 years immediately preceding the date of the advertisement for proposals pursuant to NRS 338.1692;
2. Not have been disqualified from being awarded a contract pursuant to NRS 338.017, 338.13895, 338.1475 or 408.333;
3. Not have entered into a contract with a public body to act as a construction manager as agent during the 4 years immediately preceding the date of the advertisement for proposals pursuant to NRS 338.1692;
4. Be licensed as a contractor pursuant to chapter 624 of NRS; and
5. If the project is for the construction of a public work of the State, be qualified to bid on a public work of the State pursuant to NRS 338.1379.
(Added to NRS by 2007, 2891; A 2009, 438; 2011, 3694; R 2013, 2986; R 2017, 4035; A 2021, 736, 2217, 2218)