Neb. Rev. Stat. § 76-710.03
Text of § 76-710.03
Whenever a condemner seeks to acquire lands or interest therein through eminent domain proceedings to construct power transmission lines through or over land devoted to agricultural purposes, such condemner shall be required to select a route along or following sections or one-half section lines unless such route cannot be followed without excessive and unreasonable costs to the condemner.
Laws 1978, LB 917, § 5.
Cite this section
Neb. Rev. Stat. § 76-710.03
https://lawconsensus.com/codes/nebraska/chapter-76/76-710-03/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.