LawCensus
Nebraska Revised Statutes

Neb. Rev. Stat. § 73-1116

Neb. Rev. Stat. § 73-1116 · Last amended 2025 · Text from the 2026.09.1 snapshot

Text of § 73-1116

(1) Before the construction manager begins any construction services, the authorized agency shall:

(a) Conduct an independent cost estimate for the project; and

(b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.

(2) If the construction manager and the authorized agency are unable to negotiate a contract, the authorized agency may use other contract procurement processes as provided by law. Persons or organizations who submitted proposals but were unable to negotiate a contract with the authorized agency shall be eligible to compete in the other contract procurement processes.

Laws 2025, LB660, § 16.

Cite this section

Neb. Rev. Stat. § 73-1116

https://lawconsensus.com/codes/nebraska/chapter-73/73-1116/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.