Neb. Rev. Stat. § 70-2004
Text of § 70-2004
(1) A customer-generator shall request an inspection from the State Electrical Division pursuant to subsection (1) of section 81-2124 or subsection (1) of section 81-2125 and shall provide documentation of the completed inspection to the local distribution utility prior to interconnection with the local distribution system.
(2) A customer-generator is responsible for notifying the local distribution utility of its intent to install a qualified facility at least sixty days prior to its installation and is responsible for all costs associated with the qualified facility.
(3) A local distribution utility shall not be required to interconnect with a qualified facility that fails to meet or maintain the local distribution utility's requirements for safety, reliability, and interconnection.
(4) A customer-generator owns the renewable energy credits of the electricity its qualified facility generates.
Laws 2009, LB436, § 4.
Cite this section
Neb. Rev. Stat. § 70-2004
https://lawconsensus.com/codes/nebraska/chapter-70/70-2004/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.