LawCensus
Nebraska Revised Statutes

Neb. Rev. Stat. § 52-1405

Neb. Rev. Stat. § 52-1405 · Last amended 1987 · Text from the 2026.09.1 snapshot

Text of § 52-1405

If a lender does not respond to the supplier within fifteen calendar days after receiving the lien-notification statement:

(1) If the agricultural production input is feed for livestock, a supplier who furnishes the feed has an agricultural production input lien which has priority over any security interest of the lender for the unpaid retail cost of such feed. Such lien may not exceed the amount, if any, that the sales price of the livestock exceeds the greater of the fair market value of the livestock at the time the lien attaches or the acquisition price of the livestock; or

(2) For all other agricultural production input, a supplier who furnishes such agricultural production input has an agricultural production input lien which has priority over any security interest of the lender in the specified crops or their proceeds for the lesser of:

(a) The amount stated in the lien-notification statement; or

(b) The unpaid retail cost of the agricultural production input identified in the lien-notification statement.

Laws 1987, LB 101, § 5.

Cite this section

Neb. Rev. Stat. § 52-1405