Neb. Rev. Stat. § 52-1403
Text of § 52-1403
Within fifteen calendar days after receiving a lien-notification statement, the lender shall respond to the supplier with either:
(1) A letter of commitment for part or all of the amount in the lien-notification statement and, if the letter of commitment is for only part of the amount in the lien-notification statement, then a copy of the partial commitment shall be sent to the person to whom the agricultural production input was furnished or is to be furnished; or
(2) A written refusal to issue a letter of commitment, and a copy of such refusal shall be sent to the person to whom the agricultural production input was furnished or is to be furnished.
Laws 1987, LB 101, § 3.
Cite this section
Neb. Rev. Stat. § 52-1403
https://lawconsensus.com/codes/nebraska/chapter-52/52-1403/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.