LawCensus
Nebraska Revised Statutes

Neb. Rev. Stat. § 46-1659

Neb. Rev. Stat. § 46-1659 · Last amended 2025 · Text from the 2026.09.1 snapshot

Text of § 46-1659

(1) Upon completion of the removal, breach, or abandonment of a dam, the design engineer shall file with the Chief Water Officer a completion certification.

(2) Before final approval of the removal of a dam is issued, the Chief Water Officer may inspect the site of the work and determine that all work was accomplished in substantial conformance with the application approval.

(3) Following the removal of a dam, the Chief Water Officer may report such removal to the National Performance of Dams Program and to the National Inventory of Dams.

Laws 2005, LB 335, § 59;

Laws 2025, LB317, § 297.

Cite this section

Neb. Rev. Stat. § 46-1659

https://lawconsensus.com/codes/nebraska/chapter-46/46-1659/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.