Neb. Rev. Stat. § 39-2820
Text of § 39-2820
(1) Before the construction manager begins any construction services, a contracting agency shall:
(a) Conduct an independent cost estimate for the project; and
(b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2) If the construction manager and the contracting agency are unable to negotiate a contract, the contracting agency may use other contract procurement processes. Persons or organizations who submitted proposals but were unable to negotiate a contract with the contracting agency shall be eligible to compete in the other contract procurement processes.
Laws 2016, LB960, § 20;
Laws 2019, LB583, § 14.
Cite this section
Neb. Rev. Stat. § 39-2820
https://lawconsensus.com/codes/nebraska/chapter-39/39-2820/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.