75-6906. Same; bidder withdrawing bid not to perform work on project, when. If a bidder withdraws a bid, as authorized in K.S.A. 75-6905, the awarding authority may require that such bidder shall not be allowed to perform any work on the project through subcontract agreements or by any other means including rebids.