(30 ILCS 557/15) Sec. 15. Arbitration. A contractor and governmental entity may, by mutual agreement, arbitrate the contractor's entitlement to recover the actual increase in contract time or costs incurred because of a physical condition at the site. The judgment rendered may be entered in any court having jurisdiction over the matter. (Source: P.A. 91-647, eff. 11-30-99.)