41 U.S.C. § 4309
Burden of proof on contractor
Text of § 4309
In a proceeding before a board of contract appeals, the United States Court of Federal Claims, or any other Federal court in which the reasonableness of indirect costs for which a contractor seeks reimbursement from the Federal Government is in issue, the burden of proof is on the contractor to establish that those costs are reasonable.
(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3788.)
Historical and Revision Notes
Revised
Section
Source (U.S. Code)
Source (Statutes at Large)
4309
41:256(j).
June 30, 1949, ch. 288, title III, § 306(j), as added Pub. L. 100–700, § 8(a)(1), Nov. 19, 1988, 102 Stat. 4634; Pub. L. 103–355, title II, § 2151, Oct. 13, 1994, 108 Stat. 3313.
Cite this section
41 U.S.C. § 4309
https://lawconsensus.com/codes/federal/title-41/4309/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.