6 Del. C. § 2726
Warranty claims
Text of § 2726
If, after the termination of a contract agreement, the dealer submits a warranty claim to the supplier for work performed prior to the effective date of the termination, the supplier shall accept or reject the claim within a maximum of 45 days from the day that the supplier received the claim. A claim not rejected before the deadline shall be deemed accepted. The supplier shall pay an accepted claim not later than 60 days after the day that the supplier received the claim.
Cite this section
6 Del. C. § 2726
https://lawconsensus.com/codes/delaware/title-6/2726/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.