LawCensus
Delaware Code

26 Del. C. § 910

Conditional use permit for electrical substations [For application of this section, see 85 Del. Laws, c. 44, 2]

26 Del. C. § 910 · Last amended 2025 · Text from the 2026.09.1 snapshot

Text of § 910

No county shall deny a conditional use permit to any electrical substation, along with any directly related project infrastructure, proposed to be located on unincorporated land within such county where the following conditions apply:

(1) The substation is being proposed to support the operation of a proposed renewable energy generation project of 250 MW or greater;

(2) The proposed substation would be located in a heavy industrial zone;

(3) An electrical substation is an allowed conditional use within the proposed zone; and

(4) The specific zoning district in which the proposed substation would be located already has an electric substation located in such zone with a rating of 230kv or greater as of August 3, 2023.

Cite this section

26 Del. C. § 910

https://lawconsensus.com/codes/delaware/title-26/910/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.