Duties of designers

26 Del. C. § 805 · Last amended 1994 · Text from the 2026.09.1 snapshot

Text of § 805

It shall be the duty of each designer:

(1) To contact the approved notification center and obtain the identity of operators whose facilities are listed, as required by § 803 of this title, in the area of the proposed excavation or demolition;

(2) To obtain the information prescribed in § 803(6) or (7) of this title from each operator identified as required by § 803(2) of this title;

(3) To show upon the drawing the type of each line, derived pursuant to the request made as required in paragraph (2) of this section, the name of the operator and telephone number of the approved notification center, and instructions to “notify the approved notification center not less than 2 working days, but no more than 10 working days, prior to the excavation or demolition activities.”

Cite this section

26 Del. C. § 805

https://lawconsensus.com/codes/delaware/title-26/805/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.