Text of § 13193.5

Notwithstanding any provision to the contrary in the State Water Resources Control Board’s Water Quality Control Policy on the Use of Coastal and Estuarine Waters for Power Plant Cooling, as referenced in Section 2922 of Title 23 of the California Code of Regulations, the final compliance dates for Diablo Canyon Units 1 and 2 shall be October 31, 2030. Nothing in this section prevents the state board from ordering the operator of the Diablo Canyon powerplant to conduct any other form of mitigation allowed under this chapter.